Pharma Inspection Question & Answer Part 03

Data Integrity App

 

Question 21: You have any procedure for revalidate an already established and previously validated process?

Best Answer:

Validation is required to ensure that therapeutic goods consistently meet product specifications and this principle is to be applied for all products (including complementary medicines).

There are some critical processes that must be validated and risk assessment would not justify exemption from validation (e.g. mixing for tablets/capsule/powder dosage forms). For herbal products grouping can be considered and justification included in the VMP. Markers can be used for herbal process validation.

The frequency of periodic revalidation is intentionally not defined because this will vary according to a large range of factors. Manufacturers need to determine and justify their own revalidation frequency based on a risk assessment and other relevant factors.

If the process has not been previously validated, then it should be validated retrospectively according to items 31-35 of Annex 15. When retrospective validation is inadequate, then validation according to Annex 15 is required. The scope and extent of validation should be based on risk assessment and should be conducted according to a validation master plan.

 

Question 22:

How do you deal with automatic updates of Windows or antivirus programs?

Best Answer:

Another item the FDA has started discussing more in the last few years, in conjunction with the ISPE GAMP v5 Guidance, is the concept of risk and risk-based validation. One of the things to think about with operating system and antivirus updates is the relative risk of having e.g. security problem or virus vulnerability in a system.

Sometimes the update risk may be greater than the original risk to the system itself (or vice versa). Some companies have the luxury of staff to deal with networks and server infrastructure qualification and can insulate operating systems from the software validation itself, having the responsibility to make sure that the systems are being kept current with security and antivirus updates.

As a general practice companies should periodically run a small set of standard regression tests, triggered by operating system or antivirus updates or simply on a periodic basis, to make sure that changes do not have any adverse impact on the system.

 

 Question 24: 

When a new PC is implemented, is it necessary to revalidate the software?

Best Answer: If the new PC has the same or greater capabilities than the original and is using the same version of the operating system and software, revalidation is not necessary since the functionality of the system is the same.

However, repeating the installation qualification activities to confirm that the software has been properly installed or restored properly from the backup onto the new PC is required. One detail that can make this process more efficient is to avoid overly detailed specification documents.

Avoid specifying a particular model of PC, particular processor speed, or a particular memory or disk capacity. Use of the designation “or higher” will prevent having to continually update the documentation as technology advances.

 

Question 25: 

Regarding GMP lab data integrity: once data are required, can they be modified under any circumstances?

Best Answer: Acquired data, the data coming directly from the instrument captured by the PC should be considered sacred; raw data should not be modified for any reason.

However, a second kind of data, generated during post acquisition data analysis and data processing, e.g. reintegration, changing baselines, deleting peaks that aren’t necessarily relevant to the analysis, or other calculations, are considered normal parts of data processing and may be modified under controlled circumstances as captured in audit trails.

 

Question 26: 

Software sometimes has complicated calculations or algorithms in it, for example, for the integration of chromatograph, are it necessary for the software user to validate the results?

Best Answer: Yes, calculated results must be validated. Not all of Microsoft Excel’s calculations, but any specific calculations programmed into a configurable report, e.g., CDS reporting capabilities using report templates and automatic calculations.

If calculations are used to determine whether or not a particular result is within specifications, the calculation will need to be validated with data both within and out of specification to ensure that the calculations are working properly.

This validation also evaluates the vendor’s ability to build good software and perform accurate calculations.


Question 27: 

Should the scope and extent of validation be based on risk?

Best Answer: Yes, the scope and extent of validation should be based on risk according to the manufacturer's quality risk management procedures.

Qualification and validation work is required to control the critical aspects of the particular operation and a common sense approach should be applied.


Question 28: 

Once a vendor is audited, is there a recommended time within which that vendor should be re-audited?

Best Answer: There are several factors to consider when determining the frequency of vendor audits, many related to the relative risk of the system to patient’s safety, drug product quality, and data integrity. One factor is the vendor’s performance and response from previous audits.

If they performed well, re-auditing those vendors every three years could be justified, but not longer. For other vendors that are mission critical or perhaps those that didn’t perform well in prior audits, re-auditing every 12 months is justified to increase scrutiny.

 

Question 29: 

What should the auditing approach be for software such as the CDS that is no longer supported by the vendor but is still being used within the validated state?

Best Answer: Vendors will occasionally go out of business, or more commonly, discontinue support of a particular version of their software. If a user continues to use the software, it would be at an increased level of risk because if a problem arises, the vendor may not exist to actually address the defect or willing to correct defects in obsolete versions of software they no longer support.

The risk is, however, somewhat instrument and software dependent, particularly for older instruments and software. As long as those systems are being managed and used properly, there may not be a reason to update them.

Agilent regularly considers whether or not upgrades provide enough value, enough new functionality, or enough defects fixes to be able to justify the cost, the time, and the pain involved in replacing or revalidating the system.


Question 30: 

How can I ensure and prove that SOPs are followed?

Best Answer: Through inspection. Inspections are the only way to follow up to make sure that people are doing what they have been trained to do.

29) Is performance qualification (PQ) required to be carried out for each item of critical process equipment, if process validation is performed on the same equipment?

Answer: PQ is required to be preceded by IQ and OQ.

For significant changes to equipment (eg. for new or modified items of equipment), the PQ is separate from and precedes process validation.

For minor changes not impacting on already qualified equipment (eg. to processing parameters only), process validation could be integrated in PQ and a repeated IQ and OQ may not be necessary.


Question 31: 

What about systems with no audit trail or an incomplete audit trail? What’s the work-around for such systems?

Best Answer: There are many old systems that still get used in regulated labs, and the systems work perfectly fine to do what they do. But the work-around for this is a heavy dose of procedural controls that would include handwritten records.

Depending on the criticality and the risk of the particular process that’s involved, or that the system is addressing, the procedural requirements may need to go as far as a second person verification of information or actual concurrent witnessing of the work being performed.

The purpose of the audit trail is to be able to tell the story or reconstruct the history of an electronic record, not just the creation of that record but also the changes or the deletion of records.

If the system has limited or incomplete audit trail ability, then the record must be supplemented in some other way, often taking the form of paper records. For example, a use notebook next  to an instrument. Technical controls make everybody’s life much simpler. 


“Trust but Verify “ Ronald Reagan

 

Across the internet, there are millions of resources are available which provide information about Everything.

 

If you found all content under one roof then it will save your time, effort & you will more concentrated on your important activity.

Data Integrity App


 

Our Data integrity app will helpful for understanding what Data integrity & CSV really means & How 21 CFR Part 11, EU Annex 11 & other regulatory guidelines affects in pharmaceutical Industry.

 

Data Integrity App Include 

- Basic Data Integrity Concepts

- ERES & Its Requirement

- CSV & Its best practices 

- Mock Inspection and General Q&A

- Checklist for inspection

- Inspection Readiness

- Useful SOP’s

- Stay Regulatory Compliant.

 

“Stay One Step Ahead in Pharma IT Compliance” 


Data Integrity App Link:


https://play.google.com/store/apps/details?id=com.innovativeapps.dataintegrity

 

Try our "Data Integrity" app which helps you to better understand current regulatory agencies thinking on Data Integrity & CSV.


Comments